ASX ANNOUNCEMENT
9 October 2026
Multiple High-Grade TREO Intersections
Delivered Across Nathace Hill
Highlights
• Latest significant TREO mineralisation confirmed in multiple areas across Nathace Hill
(western, north-east, and south-west), further strengthening the emerging scale of the
carbonatite system.
• Additional outstanding near surface results along the western flank reiterate its
emergence as a key exploration focus at western Nathace Hill. Results include:
26NH001 — 59m @ 1.51% TREO from 13m
Including — 24m @ 2.02% TREO from 49m
Including — 17m @ 2.46% TREO from 50m
Including — 5m @ 2.96% TREO from 55m
• 26NH001 results reinforce the continuity of mineralisation across the highly prospective
western zone, building on previously reported assays (refer to announcement 21/09/2026),
highlighted by:
26NH011 — 72m @ 1.51% TREO from surface
Including — 50m @ 2.03% TREO from surface
Including — 20m @ 4.26% TREO from surface
• High-grade assay results from north-east Nathace Hill confirms outstanding mineralisation
in closer proximity towards the carbonatite core. Results include:
26NH006 — 47m @ 1.50% TREO from 26m
Including — 14m @ 2.00% TREO from 40m
Including — 6m @ 3.03% TREO from 40m
And — 9m @ 1.53% TREO from 128m
Including — 4m @ 3.33% TREO from 128m
• Significant assays from step-out drilling at south-west Nathace Hill reveal new high-grade
mineralisation extending laterally beyond the previously interpreted footprint. Results
include:
26NH030 — 36m @ 1.50% TREO from 85m
Including — 19m @ 2.04% TREO from 86m
Including — 6m @ 3.14% TREO from 86m
Page 2 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
• Latest high-grade results provide further impetus for deeper testing, reinforcing the rationale
for the previously announced major 1,000m diamond drill hole, with its collar currently being
planned within the core area.
• Together with exceptional results previously reported across the southern and western areas
of Nathace Hill, the latest assays provide further evidence that significant high-grade zones
occur across multiple areas of the broader carbonatite system.
• A strong pipeline of assays expected in the near term as AuKing continues to define the scale
and extent of the mineralised system at Tundulu.
AuKing Mining Limited (ASX: AKN) (“AuKing” or “the Company”) is pleased to announce
outstanding TREO intersections from its RC drilling across selected areas of Nathace Hill at the
Company’s Tundulu Rare Earth Project in southern Malawi.
Further Outstanding ResultsAcross Nathace Hill
AuKing has received assays from the next batch of Tundulu drill holes and again exceptional high-
grade REE mineralisation has been identified as highlighted by the following:
26NH001 — 59m @ 1.51% TREO from 13m
Including — 24m @ 2.02% TREO from 49m
Including — 17m @ 2.46% TREO from 50m
Including — 5m @ 2.96% TREO from 55m
26NH006 — 47m @ 1.50% TREO from 26m
Including — 14m @ 2.00% TREO from 40m
Including — 6m @ 3.03% TREO from 40m
And — 9m @ 1.53% TREO from 128m
Including — 4m @ 3.33% TREO from 128m
AuKing’s Managing Director Paul Williams said: “AuKing’s Managing Director Paul
Williams said: “The latest assay results from the Tundulu drilling program continue to
provide us with various high grade REE results across various holes – some focussed around
the Nathace Hill core but others quite some distance away. The results from 26NH030 are
particularly exciting, establishing high grade REEs at depth and away from Nathace Hill,
suggesting that the magnetic anomalies established from the airborne survey might well be
marking significant rare earths mineralisation.”
“The results in the release also continue to identify mineralised zones at depth, which provide
significant confidence that our deeper drill holes are going to show continuous mineralisation
beyond 400-500m. We will continue to report the assays as this Tundulu story develops.”
Page 3 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Figure 1 – Latest Tundulu Drilling, highlighting the location of drill holes across selected areas of Nathace Hill,
including holes 26NH001, 26NH006 and 26NH030.
Figure 2 – Tundulu Drill hole 26NH001 cross section. Location along western flank, drilling towards the carbonatite
core
Page 4 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Drill hole 26NH001 further confirms the presence of high-grade, near surface rare earth
mineralisation on the western flank of Nathace Hill. Combined with exceptional intersections
reported for this prospective zone on 21st
September 2026, these latest assays provide compelling
support for increased exploration activity across the western flank, which is emerging as a
significant priority for further driliing and evaluation.
Drill holes 26NH006 and 26NH027 are among the closest holes drilled towards the interpreted
carbonatite zone to date. The significant high-grade mineralisation intersected in 26NH006,
together with broad and continuous mineralisation encountered from surface in 26NH027,
confirms that the Nathace Hill system remains well developed in this area and strengthens
evidence of its continuation towards the core of the large carbonatite.
Step-outdrillingin 26NH030 and 26NH009 at south-westNathace Hill has revealed high-grade rare
earth mineralisation beyond the previously interpreted carbaonatite footprint. These results
indiciate that the mineralised system may extend farther laterally than previously recongnised and
provide a strong basis for expanded exploration across this underexplored area.
Figure 3 – Tundulu Drill hole 26NH006 cross section. Location at north east Nathace Hill, drilling towards the
carbonatite core
Future Assays
A totalof 2,242samples have beenassayed to date, with afurther 2,047 samples atIntertek’s Perth
awaiting assays. In addition, more than 1,300m of diamond drill core samples are awaiting Malawi
export permits before being prepared for assay. AuKing expects to be reporting a steady flow of
assay results for the next few months.
Page 5 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
By Authority of the Board
For more information:
Paul Williams Kristin Rowe
Managing Director NWR Communications
M +61 419 762 487 M +61 404 88 98 96
E p.williams@aukingmining.com E kristin@nwrcommunications.com.au
Abbreviations
• TREO = Total Rare Earth Oxides – La2O3, CeO2, Pr6O11, Nd2O3, Sm2O3, Eu2O3, Gd2O3, Tb4O7,
Dy2O3, Ho2O3, Er2O3, Tm2O3, Yb2O3, Lu2O3, Y2O3 (Pm2O3 excluded by tradition)
• HREO = Heavy Rare Earth Oxides – Tb4O7, Dy2O3, Ho2O3, Er2O3, Tm2O3, Yb2O3, Lu2O3, Y2O3
• MREE = Nd, Pr, Dy, Tb
• P = Phosphorus
• NDPR% = (Nd + Pr)/TREO
• P2O5 = Phosphorus pentoxide
Competent Person’s Statement
The information in this Report that relates to Exploration Results and other technical information
from drilling at the Tundulu Rare Earths Project is based on information reviewed by Mr Mark
Mitchell whois a memberof the Australian Institute of Geoscientists. Mr Mitchell is anindependent
consultant to AuKing Mining Limited (and not an employee) and has sufficient experience which is
relevant to the style of mineralisation and type of deposit under consideration and to the activity
which they are undertaking to qualify as a Competent Person as defined in the 2012 Edition of the
‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves.’ Mr
Mitchell consents to the inclusion in the report of the matters based on his information in the form
and context in which it appears.
Page 6 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
ANNEXURE A
Tundulu drillhole location details (yellow highlighted holes reported in this
Release)
HOLE TYPE EAST NORTH RL TOTAL
DEPTH(m)
AZIMUTH DIP
26NH001 RC + DDH 800847.4 8280005 707.7 150 61 -55
26NH002 RC + DDH 800759.4 8280064 693.9 150 80 -65
26NH003 RC + DDH 800791.8 8280156 690.6 148 100 -65
26NH004 RC + DDH 801109.6 8279899 763.4 146 15 -55
26NH005 RC + DDH 801065.8 8279881 747.1 150 15 -60
26NH006 RC + DDH 801232.2 8280253 732.6 150 220 -55
26NH007 RC + DDH 800893.2 8280262 693.9 87 110 -65
26NH008 RC + DDH 800860.4 8279776 713.4 120 45 -55
26NH009 RC + DDH 800769.9 8279920 699 150 60 -65
26NH011 RC 800759.7 8280067 693.8 150 270 -55
26NH012 RC 800801.4 8280209 687.9 129 310 -55
26KH013 RC 801527 8280916 667.3 150 35 -65
26NH014 RC 800867.9 8279929 714.4 150 220 -70
26NH023 RC + DDH 801376 8280303 690.1 400.42 220 -55
26NH027 RC 801012.5 8280259 714.2 129 180 -55
26KH028 RC 801476.2 8281135 658.4 148 180 -65
26NH029 RC 801111.1 8279858 743.9 150 10 -55
26NH030 RC 800770 8279919 699.2 148 250 -75
26NH031 RC 800889.2 8280262 693.9 135 360 -55
26NH032 RC + DDH 801423.4 8280349 679.3 510.62 225 -55
26NH033 RC 801286.1 8280237 736.1 150 210 -55
26NH034 DDH 801290.5 8279909 742.7 250 300 -55
26NH024A DDH 801295 8279909 742.7 251.19 355 -55
[Note – references to RC + DDH in the “TYPE” column indicate planned diamond drilling
tails at the base of the RC-drilled hole]
Page 7 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
ANNEXURE B
Assay Results from LatestDrill Holes (Drill holes 26NH001, 006, 030, 009, 002, 007, 012,027,031)
Hole: 26NH001
Page 8 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Page 9 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Hole: 26NH006
Page 10 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Page 11 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Hole: 26NH030
Page 12 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Page 13 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Hole: 26NH009
Page 14 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Page 15 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Hole: 26NH002
Page 16 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Page 17 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Hole: 26NH007
Page 18 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Hole: 26NH012
Page 19 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Hole: 26NH027
Page 20 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Page 21 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Hole: 26NH031
Page 22 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Page 23 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
JORC Code, 2012Edition – “Multiple Compelling High-Grade TREO Intersections
Delivered Across Nathace Hill”
Section 1 Sampling Techniques and Data
Criteria JORC Code explanation Commentary
Sampling
techniques
• Nature and quality of sampling (eg cut channels,
random chips, or specific specialised industry
standard measurement tools appropriate to the
minerals under investigation, such as down hole
gamma sondes, or handheld XRF instruments,
etc). These examples should not be taken as
limiting the broad meaning of sampling.
• Include reference to measures taken to ensure
sample representivity and the appropriate
calibration of any measurement tools or systems
used.
• Aspects of the determination of mineralisation
that are Material to the Public Report. In cases
where ‘industry standard’ work has been done
this would be relatively simple (eg ‘reverse
circulation drilling was used to obtain 0.5 m
samples from which 3 kg was pulverised to
produce a 30 g charge for fire assay’). In other
cases more explanation may be required, such as
where there is coarse gold that has inherent
sampling problems. Unusual commodities or
mineralisation types (eg submarine nodules) may
warrant disclosure of detailed information.
• Reverse Circulation (RC) drilling was
completed using a face-sampling hammer.
• All RC drillholes were sampled on continuous 1
m intervals irrespective of lithological
boundaries.
• Sample material was collected from the
cyclone into green mining bags before being
processed using a manual three-tier riffle
splitter to obtain representative calico
samples. Where wet or clay-rich conditions
prevented representative riffle splitting, a
documented spear sampling protocol was
used.
• Geological logging was completed on every
metre using representative RC chips retained
from each interval.
• Sampling procedures were undertaken in
accordance with Company Technical Work
Guideline TWG001.
• The massive nature of the mineralised host unit
is amenable to an industry standard RC
sampling methodology being applied.
• No diamond core assay results are reported in
this announcement. Diamond core sampling
has not yet been undertaken.
Drilling
techniques
• Drill type (eg core, reverse circulation, open-hole
hammer, rotary air blast, auger, Bangka, sonic,
etc) and details (eg core diameter, triple or
standard tube, depth of diamond tails, face-
sampling bit or other type, whether core is
oriented and if so, by what method, etc).
• Reverse Circulation drilling utilised a face-
sampling hammer with compressed air.
• Drillholes were completed at the planned
orientations using surveyed collar locations
and downhole surveys where appropriate.
• Representative drill chips were collected at 1 m
intervals for geological logging and sampling.
• Diamond drilling is currently being undertaken
by Thompson Drilling in Malawi using NQ-
diameter diamond core drilling.
Drill sample
recovery
• Method of recording and assessing core and chip
sample recoveries and results assessed.
• Measures taken to maximise sample recovery
and ensure representative nature of the samples.
• Whether a relationship exists between sample
recovery and grade and whether sample bias may
have occurred due to preferential loss/gain of
fine/coarse material.
• The bulk weight of each 1 m RC sample was
recorded prior to sample splitting, providing a
quantitative record of sample recovery and
enabling identification of intervals with
anomalously low sample return.
• Bulk sample weights were recorded as a quality
control measure to monitor sample return.
Generally, the range of those weights were 35-
40kgs.
• No relationship between sample recovery and
assay grade has been established as this
programme is early-stage reconnaissance RC
drilling.
Logging • Whether core and chip samples have been
geologically and geotechnically logged to a level
of detail to support appropriate Mineral Resource
estimation, mining studies and metallurgical
studies.
• Whether logging is qualitative or quantitative in
nature. Core (or costean, channel, etc)
• Representative RC chip trays were prepared and
geologically logged in full at 1 m intervals for all
drillholes.
• Logging included lithology, weathering,
alteration, mineralisation, veining, carbonate
content, magnetic response, grain size, colour
and other relevant geological observations.
Page 24 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Criteria JORC Code explanation Commentary
photography.
• The total length and percentage of the relevant
intersections logged.
• Logging was mostly qualitative in nature and
completed to a level of detail considered
appropriate to support geological interpretation
and future Mineral Resource estimation.
• Geological observations were recorded
independently of any assay information in
accordance with Company logging procedures.
Sub-sampling
techniques
and sample
preparation
• If core, whether cut or sawn and whether quarter,
half or all core taken.
• If non-core, whether riffled, tube sampled, rotary
split, etc and whether sampled wet or dry.
• For all sample types, the nature, quality and
appropriateness of the sample preparation
technique.
• Quality control procedures adopted for all sub-
sampling stages to maximise representivity of
samples.
• Measures taken to ensure that the sampling is
representative of the in situ material collected,
including for instance results for field
duplicate/second-half sampling.
• Whethersamplesizesare appropriatetothe grain
size of the material being sampled.
• Representative primary samples were obtained
using a manual three-tier riffle splitter.
• Wet or clay-rich samples unsuitable for riffle
splitting were collected using a documented
multi-pass spear sampling methodology.
• Approximately 2–4 kg of sample was collected
into pre-numbered calico bags.
• Remaining reject material was retained in
labelled plastic bulker bags.
• Sample preparation procedures were designed
to minimise sample bias and maintain
representative sampling throughout the drilling
program
Quality of
assay data and
laboratory
tests
• The nature, quality and appropriateness of the
assaying and laboratory procedures used and
whether the technique is considered partial or
total.
• For geophysical tools, spectrometers, handheld
XRF instruments, etc, the parameters used in
determining the analysis including instrument
make and model, reading times, calibrations
factors applied and their derivation, etc.
• Nature of quality control procedures adopted (eg
standards, blanks, duplicates, external
laboratory checks) and whether acceptable
levels of accuracy (i.e. lack of bias) and precision
have been established.
Due to the refractory nature of some REE-bearing
minerals, lithium-borate fusion was selected to
provide a total digestion.
Samples were prepped in Intertek’s Kitwe, Zambia
laboratory, before being shipped to their Perth lab
for lithium Borate fusion digestion assay fusion
Samples were pulverised and fused using a lithium
borate flux at high temperatures which completely
break down the matrix of the material, ensuring
refractory components are entirely dissolved. The
samples are finished by either ICP-OES or ICP-MS
for major and trace elements respectively.
A definitive QAQC program was implemented to
provide verification of the sample procedure, the
sample preparation and the analytical precision and
accuracy of the primary laboratory, which includes
the following:
Certified Reference Material (CRM) samples: 2 (two)
types of standards sourced from AMIS
standards/blanks, including AMIS0356/AMIS0939,
were inserted 1 in every 20 samples
Coarse blank samples: Inserted 1 in every 20
samples to monitor cross contamination
The laboratory also inserted QAQC samples,
including laboratory standards and CRMs.
Overall, 12.5% of the samples submitted to the
primary assay lab were QAQC samples. The QAQC
procedures undertaken show that returned results
are within acceptable limits.
Page 25 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Criteria JORC Code explanation Commentary
• Results are considered as acceptable by the
Competent Person and the drill samples are
considered to be suitable for reporting of
exploration results.
Verification of
sampling and
assaying
• The verification of significant intersections by
either independent or alternative company
personnel.
• The use of twinned holes.
• Documentation of primary data, data entry
procedures, data verification, data storage
(physical and electronic) protocols.
• Discuss any adjustment to assay data.
• Geological logging was completed using
standardised electronic logging templates.
• All geological observations were recorded prior
to receipt of analytical results.
• Logging and sampling procedures were
undertaken by Company geologists following
documented Company procedures.
• Sample submissions, QAQC insertion and
laboratory dispatch were recorded using
Company sample management systems.
• Hole 26NH004 was twinned near to historical
drill hole TUO71 and holes 26NH005 and
26NH029 were drilled nearby historical drill
holes. As noted in the body of the
announcement, this was done in order to
validate historical geological interpretations for
future resource studies and establish internal
lithological markers for ongoing logging, as no
historical RC chips or drill core have been
retained by previous explorers.
• No adjustments have been made to the data
other than conversion to oxides using standard
stoichiometry conversion factors obtained
from JCU
• Standard conversion factors were
Ce2O3 -1.1713
Dy2O3 -11477.
Er2O3 - .1435
EU2O3 – 1.1579
Gd2O3 - 1.1526
Ho2O3 – 1.1455
La2O3 – 1.1728
Lu2O3 – 1.1371
Nd2O3 – 1.1664
Pr6O11 – 1.2082
Sm2O3 – 1.1596
Tb4O7 – 1.1762
Tm2O3 – 1.1421
Y2O3 – 1.2699
• Yb2O3 – 1.1387
Location of
data points
• Accuracy and quality of surveys used to locate
drill holes (collar and down-hole surveys),
trenches, mine workings and other locations
used in Mineral Resource estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
• Drillhole collar locations were determined
using a handheld GPS.
• Grid system is in WGS 84 UTM Zone 36 South
• Elevations were determined from previously
reported LiDAR drone survey.
Data spacing
and
distribution
• Data spacing for reporting of Exploration Results.
• Whether the data spacing and distribution is
sufficient to establish the degree of geological
and grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation
procedure(s) and classifications applied.
• Whether sample compositing has been applied.
• Drillhole spacing is irregular and dependant on
the target areas.
• It is considered that the spacing of samples
used is sufficient for the current stage of
exploration.
• No drill sample compositing has occurred.
Orientation of
data in relation
to geological
structure
• Whether the orientation of sampling achieves
unbiased sampling of possible structures and the
extent to which this is known, considering the
deposit type.
• Drillholes were oriented to test the interpreted
geometry of the Tundulu carbonatite intrusive
complex based on historical drilling, geological
mapping and airborne magnetic data.
• Step-out drillholes were designed to test
Page 26 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Criteria JORC Code explanation Commentary
• If the relationship between the drilling orientation
and the orientation of key mineralised structures
is considered to have introduced a sampling bias,
this should be assessed and reported if material.
interpreted extensions of the carbonatite
system beyond historically drilled areas.
• The true orientation of individual carbonatite
phases has not yet been established; reported
intercepts are downhole lengths and true
widths are currently unknown.
• No orientation-related sampling bias has been
identified.
Sample
security
• The measures taken to ensure sample security. • Samples remained under Company
supervision from collection through logging and
preparation.
• Calico samples were sealed within labelled
polyweave bags for transport in company truck
to warehouse facilities.
• Sample batches were documented using
Company sample submission registers prior to
dispatch to the preparation and analytical
laboratories.
• Remaining RC reject material was retained
onsite in labelled green mining bags where
appropriate.
• Diamond core remains under Company
supervision during transport from the drill site
to the Company's Zomba core processing and
storage facility, where logging, photography,
cutting and sampling are undertaken.
Audits or
reviews
• The results of any audits or reviews of sampling
techniques and data.
• Sampling and logging procedures were
undertaken in accordance with Company
Technical Work Guideline TWG001.
• Internal reviews of geological logging, sampling
procedures and QAQC protocols are
undertaken throughout the drilling program.
Section 2 Reporting of Exploration Results
Criteria JORC Code explanation Commentary
Mineral
tenement and
land tenure
status
• Type, reference name/number, location and
ownership including agreements or material
issues with third parties such as joint ventures,
partnerships, overriding royalties, native title
interests, historical sites, wilderness or national
park and environmental settings.
• The security of the tenure held at the time of
reporting along with any known impediments to
obtaining a license to operate in the area.
• AuKing’s Tundulu REE project is located in
southeastern Malawi, approximately 90 km
east of Blantyre.
• The Tundulu Project lies within Exploration
Licence No. EL0731/24 which was granted on
27 May 2024.
• EL0731/24 covers an area of approximately
91.5 square kilometres.
• The Licence is currently 100% held in the name
of Malawian registered Green Exploration Ltd, a
subsidiary of Tusker Minerals Limited and, as
set out in the above release, is the subject of a
transfer approval with the Malawi MMRA.
• There are no known third-party interests
affecting the Licence.
• There are no known impediments to operating
in the project area.
Exploration
done by other
parties
• Acknowledgment and appraisal of exploration by
other parties.
• The Company confirms that it is not aware of
any new information or data that materially
affects the information included in the original
announcement dated 17/04/2026.
Geology • Deposit type, geological setting and style of
mineralisation.
• The Company confirms that it is not aware of
any new information or data that materially
affects the information included in the original
announcement dated 17/04/2026.
Page 27 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Criteria JORC Code explanation Commentary
Drill hole
information
• A summary of all information material to the
under-standing of theexplorationresultsincluding
a tabulation of the following information for all
Material drill holes:
• easting and northing of the drill hole collar
• elevation or RL (Reduced Level – elevation
above sea level in metres) of the drill hole
collar
• dip and azimuth of the hole
• down hole length and interception depth
• hole length
• If the exclusion of this information is justified on
the basis that the information is not Material and
this exclusion does not detract from the
understanding of the report, the Competent
Person should clearly explain why this is the case.
• The Company confirms that it is not aware of
any new information or data that materially
affects the information included in the original
announcement dated 17/04/2026.
Data
aggregation
methods
• In reporting Exploration Results, weighting
averaging techniques, maximum and/or
minimum grade truncations (e.g. cutting of high
grades) and cut-off grades are usually Material
and should be stated.
• Where aggregate intercepts incorporate short
lengths of high-grade results and longer lengths
of low grade results, the procedure used for such
aggregation should be stated and some typical
examples of such aggregations should be shown
in detail.
• The assumptions used for any reporting of metal
equivalent values should be clearly stated.
• Data have not been aggregated.
• The exploration results are reported with no
TREO cutoff grade
• No sample weighting was applied, nor high
grade cuts. Only interval length weighting
applied, down hole mineralisation is a
weighted average using the cut- offs above
to the data in Appendix 1, see bold
highlights
Relationship
between
mineralisation
widths and
intercept
lengths
• These relationships are particularly important in the
reporting of Exploration Results.
• If the geometry of the mineralisation with respect to
the drill hole angle is known, its nature should be
reported.
• If it is not known and only the down hole lengths are
reported, there should be a clear statement to this
effect (e.g. ‘down hole length, true width not known’).
• Reported intersections are downhole lengths.
The true widths of any mineralised intervals are
not yet known.
• No relationship has been established at
present due to the early stage of exploration.
• With additional exploration this will be
reviewed.
•
Diagrams • Appropriate maps and sections (with scales) and
tabulations of intercepts should be included for
any significant discovery being reported. These
should include, but not be limited to a plan view of
drill hole collar locations and appropriate
sectional views.
• All relevant data is reported within the body of
this announcement.
Balanced
Reporting
• Accuracy and quality of surveys used to locate
drill holes (collar and down-hole surveys),
trenches, mine workings and other locations
used in Mineral Resource estimation.
• Where comprehensive reporting of all Exploration
Results is not practicable, representative
reporting of both low and high grades and/or
widths should be practiced to avoid misleading
reporting of Exploration Results.
• All relevant data is reported within the body of
this announcement.
• Only pertinent results are included given the
scope this announcement
Other
substantive
exploration
data
• Other exploration data, if meaningful and material,
should be reported including (but not limited to):
geological observations; geophysical survey
results; geochemical survey results; bulk samples
- size and method of treatment; metallurgical test
results; bulk density, groundwater, geotechnical
and rock characteristics; potential deleterious or
contaminating substances.
• All relevant data is reported within the body of
this announcement. No material information
has been withheld for the project.
Page 28 of 28
AuKingMining Limited P 07 3535 1208 W www.aukingmining.com
Criteria JORC Code explanation Commentary
Further work • The nature and scale of planned further work (e.g.
tests for lateral extensions or depth extensions or
large- scale step-out drilling).
• Diagrams clearly highlighting the areas of possible
extensions, including the main geological
interpretations and future drilling areas, provided this
information is not commercially sensitive.
• Selective drill program to test the lateral
extents, vertical depths, widths, and
continuation of known mineralization and test
new targets under post-mineralization
sedimentary cover identified from the
outcomes of this survey.
Share your feedback