Proposed drilling program at Mkuju Uranium Project
Released
Released
Announcement PDF
Auking Mining Limited
ASX:AKN
Suite 2208, Level 22
127 Creek Street
Brisbane Queensland 4000
ABN 29 070 859 522
Phone 07 3535 1208
www.aukingmining.com
19 February 2024
ASX RELEASE
AuKing to proceed with extensive drilling at Mkuju;
drilling tenders being called
AuKing Mining Limited (ASX: AKN) is pleased to announce details of its proposed
Stage 2 exploration drilling program at the Mkuju Uranium Project in southern
Tanzania.
AuKing CEO, Paul Williams said AuKing is looking forward to proceeding with its Stage 2
drilling program at Mkuju, after the initial Stage 1 activities identified some significant areas
of uranium mineralization.
“The planned 75 drill hole (11,000m) air core/RC drilling program at Mkuju is expected to
commence in late May, after cessation of the wet season. The work we carried out last year
in the Stage 1 program identified several key target areas for the proposed drilling. Under
local content rules in Tanzania a tender is required to be called from drilling service
companies and that process has now commenced,” Mr Williams said.
2024 Mkuju Exploration Program (Stage 2)
(a) Program Aims
There are some key aims associated with the proposed Stage 2 drilling program at
Mkuju as follows:
• Carry out the first detailed exploration drilling program in this region to the immediate
south of Nyota;
• Test the high priority target areas that have emerged from the Stage 1 program and
sit within the historical Mantra Resources radiometric survey;
• Carry out a drilling pattern of several holes for each target area in order to maximise
the prospects of intersecting uranium mineralization;
• Test the potential mineralized extents of certain target areas in the three new Eastern
PLs that coincide with the Mantra radiometric anomaly; and
• Generally, provide the basis for a further Stage of drilling that will primarily be
focused on establishing an initial mineral resource estimate (MRE) at Mkuju.
1
(b) Proposed activities
The principal activity of the Stage 2 program will be the planned 75 drill hole (circa
11,000m) program utilizing a track-mounted air core/RC drilling rig. The proposed drill
hole locations are shown in Figure 1 below. This particular rig is being sought for the
program for two main reasons:
• The access tracks and general terrain in the proposed drill sites are very rough and
not at all suitable for the standard truck-mounted drilling rig; and
• Having the ability to switch to RC drilling could be important if a drill hole is in
mineralization but the air core drilling does not have the capacity to go deeper in the
hole.
It is likely that (subject to crew availability) further soil and rock chip sampling and
general mapping will also be undertaken, particularly in the new eastern PL areas, with a
focus on continuing to see correlation between sampled material and the Mantra
radiometric anomaly.
Another aspect of the planned drilling is to continue the practice of utilizing a portable
pXRF unit out in the field to test potential mineralization of the drilling samples. The
general approach would be to continue drilling in a hole location (beyond the planned
number of holes in that location) in order to maximise the data that is obtained from this
location. The flip aide to this approach is if drilling in a certain location fails to identify any
mineralization after a few planned holes, then a decision may be taken to mobilise the rig
to another area and not just drill for the sake of drilling. On that basis, the planned 75
holes (over an average 150m depth) is likely to be a reasonable estimate of the additional
drilling in good areas, and less drilling in the areas of little success.
Furthermore, in the event of some success with the drilling program, there may also be
the opportunity to secure an additional drilling rig for mobilization to the area in order to
bring forward some of the planned Stage 3 MRE drilling activities.
(c) Stage 2 Program Time Period
There is an expectation of mobilizing the drilling rig in late May/earlyJune at the latest.
Knowledge gained from last year’s activities is that the ground is still very wet (and
virtually inaccessible) until 2 months after completion of the annual wet season in the
Mkuju area. At the other end of the calendar, the preference will be to cease operations
by the end of November and not taking risks with an early-onset of rainfall in December.
That effectively provides 5 months of concerted drilling time. Even though the air
core/RC drilling should proceed relatively quickly, there will always be machinery
breakdowns and failures as well as some time delays with the rig being trammed around
to the various target sites.
Samples derived from the drilling will be regularly sent to the laboratory for assay, as the
drilling continues.
2
Figure 1 – Proposed Stage 2 Mkuju drilling locations.
(d) Personnel/Drilling Contractors
AuKing has now established a reliable and very competent team of field geologists and
field hands as a result of the drilling that was undertaken last year at Mkuju.
3
From a drilling rig perspective, because of the size of the program (more than US$100k)
AuKing is required to carry out a tender for the drilling services under the Tanzanian
local content rules. This process has already commenced.
(e) Proposed Budget
Based on the experiences gained from the Stage 1 drilling in 2023, AuKing has budgeted
an estimated US$800k cost for the Stage 2 program (including a 10% project
contingency). This estimate may vary depending on the levels of success being achieved
with the drilling (for example, another rig may be brought to site to commence MRE
drilling in the event of success in certain target areas). AuKing will announce details
shortly of its funding plans for the Stage 2 program, with the intention being to minimize
significant dilution to existing holders.
For more information, please contact:
Paul Williams
Chief Executive Officer
Mobile +61 419 762 487
p.williams@aukingmining.com
Gareth Quinn
Investor Relations
Mobile + 61 417 711 108
gareth@republicpr.com.au
About AuKing Mining
AuKing Mining (ASX:AKN) is a mining exploration company focused on uranium, copper and
zinc projects in both Tanzania and Australia.
AuKing is focussed on the exploration and development of six uranium and copper projects in
Tanzania including:
Mkuju – near to the world class Nyota uranium project in southern Tanzania; the subject of
significant previous exploration
Manyoni/Itigi – the subject of significant exploration situated in central Tanzania, just west of
Dodoma
Mpanda/Karema – prospective copper areas in western Tanzania that were the subject of historic
mining operations but largely untouched by modern exploration methods.
The Company also holds the Koongie Park Copper Zinc Project in Western Australia’s Halls Creek
Region hosts a JORC resource and is neighboured by several significant mining and development
operations including Nicholson’s Gold Mine and Savannah Nickel Mine. Koongie Park has already
been the subject of significant exploration drilling and analysis since the 1970’s, hosting over 300 RC
and diamond drill holes consisting of more than 60,000m of drilling in total. AuKing announced the
promising results of its Koongie Park Scoping Study in June 2023 on a proposal to commence
mining operations around a central processing facility at Sandiego.
For further information
www.aukingmining.com